Airfield Lighting Rehabilitation & Electrical Vault Replacement

- A $25.4M major resiliency initiative to help protect critical airfield infrastructure from hurricanes and tropical storms while minimizing operational disruptions.
- The project includes installation of more than 1,000 elevated, watertight runway and taxiway lights designed to better withstand storm surge flooding, more than 140 new backlit signs, and a new Airport Lighting Control and Monitoring System.
- Also included is replacement of the airport’s electrical vault with a new storm-resilient design.
- Construction commenced on July 13, 2026, with completion expected in approximately 20 months.
- Anticipated Airfield Closures:
- Taxiway A between the Runway 05 approach end and Taxiway C will be closed nightly from 7:00 PM to 7:00 AM beginning October 11 through November 26, with the taxiway reopening each day at 7:00 AM.
- Please check NOTAMS for the most up to date closure information.
North Road Terminal Interior Improvements

- The project will modernize the terminal’s interior through phased renovations designed to enhance functionality, durability, and the overall customer experience.
- Scope includes selective demolition, upgraded finishes, casework and furnishings, and improvements to mechanical, electrical, plumbing, and HVAC systems.
- Work will be coordinated to maintain ongoing airport operations and access to the Rental Car Agencies will be available at an adjacent onsite modular facility.
- Construction commenced in June 2026 and is expected to be completed in December 2026.
- Main parking lot and Terminal Drive closures are scheduled for late October through late November.
- Rental car customers will be detoured via Tower Drive.
Security Improvements Phase II

- Construction is underway and is expected to be completed in December 2026.
General Aviation Terminal Roof Replacement

- The project has successfully reached Substantial Completion and is currently progressing through final punch list items and closeout activities.
Fuel Farm Improvements

- Improvements include resiliency upgrades, a new operator office, modernizing safety systems, access road widening, and the addition of a new tank for Sustainable Aviation Fuel (SAF).
- These efforts are vital to improving airport operations and infrastructure while maintaining safety and efficiency.
- Construction is underway and is expected to be completed in early 2027.
Facilities Improvements

- The project continues to make excellent progress and is in its final stages, with Substantial Completion anticipated in December 2026.
East Quad Hangar Door Replacement

- The eastern portion of T-Hangar Buildings 2100 and 2200 are undergoing replacement of twenty (20) existing sliding hangar doors with new, single panel, power operated hydraulic hangar doors.
- Project construction is currently on hold, with work expected to resume once a path forward for completing the remaining construction activities is finalized.
- The Leasing Office will continue to work closely with affected tenants to help ensure a smooth process.
404 Citation Point Hangar Renovation

- Construction commenced in July 2026, with anticipated completion in December 2026.
Airport Office Building Exterior Door Improvements

- Electrical installation work associated with the new sliding door system has been completed. Door installation is expected to begin within the next 3 to 4 weeks, marking the next major milestone for the project.
Additional Upcoming Projects:
- 2026 Perimeter Fence Replacement
- North Road & Aviation Drive Sidewalk Repairs
Recently Completed Projects
- 2000-Series Hangars (Buildings 2000-2600) — Roof Restoration
- 3000-Series Hangars (Buildings 3000, 3100, and 3200) — Roof Restoration
- North Road Terminal Exterior Renovations
- Pilot Shop Renovations
- South Fueler Rehabilitation
- General Aviation Terminal Interior and Exterior Improvements
- Runway 05-23 Interior Perimeter Roads
- Airport Road Landscaping Improvements
- Taxiway A&B Safety Improvements
- GA Apron Asphalt Repaving
- GA Apron Lighting Replacement
- Taxiway A3 Relocation
- Runway 05-23 Drainage and Safety Improvements
- Taxiway D Emergency Repairs
- NAVAIDs Upgrade
- GA Apron Joint Sealant Replacement
- 2024 Perimeter Fence Replacement
- GA Terminal Long-Term Parking Lot Expansion
- Pilot’s Lounge Renovation
- Exotic Clearing


